The Shanghai–Kunming high-speed railway is a high-speed railway line. It was built in stages and completed on 28 December 2016.[1] It is part of the CRH's system of passenger-dedicated lines, beginning in Shanghai and ending in Kunming, the capital of Yunnan Province. Following a fairly similar route to the older "conventional" Shanghai–Kunming Railway, the Shanghai–Kunming high-speed railway passes through four more provincial capitals, the cities of Hangzhou, Nanchang, Changsha, and Guiyang.[2]

Status

The entire line is operational. The last section, Guiyang–Kunming, was opened on 28 December 2016. In November 2017, Chinese media reported that traffic safety was endangered due to quality issues with the construction; furthermore, the construction company committed fraud and illegal subcontracting. On some sections, operational speeds were reduced from 300 kilometres per hour (190 mph) to 70 kilometres per hour (43 mph), due to some problems in construction, confirmed by the state media.[3]

Components

Section Description Designed
speed
(km/h)

Length
(km)

Construction
start date

Open date
Shanghai–Kunming
high-speed railway

HSR Corridor connecting East, Central and Southwest China. It consists of three sections connecting Shanghai, Hangzhou, Changsha and Kunming. 350 2,258 2009-02-26 2016-12-28
Shanghai–Hangzhou section
(Shanghai–Hangzhou high-speed railway)
HSR connecting Shanghai and Hangzhou. 350 150 2009-02-26 2010-10-26
Hangzhou–Changsha section
(Hangzhou–Changsha high-speed railway)
HSR connecting Hangzhou & Changsha, via Nanchang. 350 933 2009-12-22 Hangzhou–Nanchang Section: 2014-12-10[4]
Nanchang–Changsha Section: 2014-09-16[5]
Changsha–Kunming section
(Changsha–Kunming high-speed railway)
HSR connecting Changsha & Kunming 350 1,175 2010-03-26 Changsha–Xinhuang Section: 2014-12-16[6]
Xinhuang-Guiyang Section: 2015-06-18
Guiyang-Kunming section: 2016-12-28