Parali Thermal Power Plant is located at Parali Vaijnath in Beed district of Maharashtra. The power plant is one of the coal based power plants of Maharashtra State Power Generation Company (Mahagenco).[1]

Installed Capacity

Stage Unit Number Installed Capacity (MW) Date of Commissioning Status
Stage I 1 30 1970 August Abandoned
Stage I 2 30 1971 March Abandoned.
Stage II 3 210 1979 April Abandoned.
Stage II 4 210 1980 July Abandoned.
Stage II 5 210 1981 January Abandoned.
Stage III 6 250 2007 Running.
Stage III 7 250 2010 Running.
Stage IV 8 250 2016 Running.[2]